Total marks: 80 1.a. Explain Principles of management given by Mr. Henry Fayol. (10 marks) 11617 1.b. Explain the functions covered by Construction Management. (10 marks) 8058 2.a. Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities. (10 marks) 12286 2.b. What is Gantt bar chart? Also explain its drawbacks. (10 marks) 11074 3.a. Following is the data of the associated with PERT Project. i) Determine the variance of the project. ii) What is the probability of completing the project in 29 days? iii) What is the scheduled duration with 90% probability? (10 marks) 12287 3.b. Define time and cost overrun. What are the common causes of time and cost overruns? Explain the corrective measures for the same. (10 marks) 12281 4.a. Following Table shows activities, their durations and labour requirements: i) Prepare histograms based on EST & LST Schedule. ii) Which schedule you will prefer & why? (10 marks) 12289 4.b. Explain: - i) Resource Levelling ii) Resource Smoothening. (10 marks) 8098 5.a Determine the optimum cost and optimum duration for the project. The data for each activity of the network is given in the following table. Indirect cost = Rs.160 / per day. (10 marks) 12305 5.b. Define Accident. Which are the main causes of accidents on construction sites? Also explain the precautionary measures to avoid accidents. (10 marks) 8120 6. Write notes on followings: (Any five) 6.a. Role of inspection in quality control. (4 marks) 11063 6.b. Principles of accounting. (4 marks) 12291 6.c. Economic appraisal criteria's. (4 marks) 12292 6.d. Work Breakdown Structure. (4 marks) 8084 6.e. Time Value of Money. (4 marks) 8100 6.f. A-B-C analysis. (4 marks) 8101 6.g. Man-power planning. (4 marks) 12293 Civil Engineering (Semester 8)
Total time: 3 Hours INSTRUCTIONS
(1) Question 1 is compulsory.
(2) Attempt any three from the remaining questions.
(3) Draw neat diagrams wherever necessary.
Activity A B C D E F G H I J K L M N Preceding Activity -- A A B D D D B C, E G F, I, J K G, H M Duration (days) 5 2 6 12 10 9 5 9 1 2 3 9 7 9
Activity A B C D E F G Preceding activity -- -- A B A B C & D to (days) 6 5 4 4 4 2 4 tm (days) 9 8 7 7 7 5 10 tp (days) 12 17 22 16 10 8 22
Z -3 -2 -1 0 1 2 3 P (%) 0.13 2.28 15.87 50 84.13 97.72 99.87
Activity A (10-20) B (10-30) C (20-50) D (30-40) E (30-50) F (40-50) Duration 8 11 6 5 8 5 Labours 3 4 2 5 3 3
Activity Normal Time (days) Crash Time (days) Normal Cost (Rs.) Crash Cost (Rs.) 10-20 2 2 1000 1000 10-30 7 3 500 900 20-30 6 3 300 420 20-40 5 4 200 250 30-40 0 0 0 0 30-50 9 4 600 900 40-60 11 6 600 1000 50-60 6 3 700 910
Source: https://www.ques10.com/p/41093/construction-management-question-paper-dec-16-ci-1/
Posted by: jenniecoerescoleates.blogspot.com
Posting Komentar untuk "Construction Engineering And Management Previous Question Papers"